Chandler: connecting continents
Contacts

Chandler GmbH

Mittelweg 55

20149 Hamburg

Phone: +49 40 238 017-0

Fax: +49 40 238 017-19


News

30.11.2011

Presentation of group of companies Chandler in Tomsk

On November, 2nd ” the presentation of group of companies Chandler ” took place in a building of the Russian-German house. At a meeting there were representative vice mayor on capital construction of Tomsk Marchenko A.V., representatives of administration of Altay territory, representatives of department of the international and regional communications of Tomsk and other […]

read this article

16.11.2011

The delivery of 367 modules on a building site of the Federal Center of Neurosurgery Novosibirsk is completed

On November, 15th, 2011  the company Chandler has delivered the last 12 of 367 modules for the Novosibirsk Federal Center of neurosurgery. Besides  the modules from Germany on a building site  54 eurowaggons with an additional equipment have arrived there,too. The delivery of the medical modules was carried out on a following route: ADK Factory […]

read this article

13.10.2011

The 367-th module for the Neurosurgery Centre in Novosibirsk left the factory in Germany.

  The 367-th module for  the  Neurosurgery Centre in Novosibirsk left the factory in Germany. Remind you that the construction of this project is conducting by “Rostechnologies”. All modules for center were assembled and equipped in Germany. The latest module was produced in the end of September of 2011-th. As you can see on the […]

read this article

10.10.2011

Transport and Logistics 2011

From the 20th till the 22nd of September an exhibition-conference “Transport and logistic 2011”took place in the exhibition center of the Antverpen, Belgium, which is very popular and famous among manufacturers, transport companies and forwarding agents. On the exhibition were introduced leaders of the European transport market and company Chandler had its own stand as […]

read this article

05.10.2011

The transporting of heavy-weight equipment to the Salekhard, Nizhnevartovsk TPS

Within  the project of delivery General Electric’s energetic equipment for the building of  the new power generating unit company Chandler has successful transported 3 heavy-weight units (steam turbine weight 291 ton, gas-generator – 218 ton and generator for steam turbine – 188 ton) from the board of of the STK type craft on the special prepared for […]

read this article

20.09.2011

Olympic Games in the City of Sochi

Olympic Games in the City of Sochi CHANDLER has developed its unique projects for delivering the above cargo taking into account the characteristics of the local relief & climate and the limited capacity of the current rail and motor road network. In modern Russian history, the Sochi-2014 Project is the largest project of integrated renewal […]

read this article

02.09.2011

Construction of a third power-generating unit at the Nizhnevartovsk TPS

Success of the vast investment project – construction of third Nijnevartovsk power-generating unit SDPS – depends on the logistic company as much as on general contractor and investors. Construction of new buildings, assembling of equipment directly depends on organized and professional work of shipping company. In April 2011 American diversified corporation “General Electric”, world first […]

read this article

25.05.2011

Delivery of “General Electric” energy equipment to Nijnevartovsk SDPS

Through the assistance of the project of delivery of “General Electric” energy equipment, “Chandler” started to construct a moorage Ro-Ro and temporary road to the construction site of new power generating unit on Nijnevartovsk SDPS. Delivery of the main heavyweight equipment is planned to the end of summer 2011: • Combustion turbine 9 FA – […]

read this article

23.05.2011

Компания Chandler приняла участие в выставке Break Bulk 2011

С 17 по 19 мая в центральном выставочном центре г. Антверпен, Бельгия состоялась 6-я ежегодная выставка – конференция Break Bulk 2011, широко известная и популярная среди производителей, транспортников и экспедиторов. На выставке были представлены лидеры европейского транспортного рынка- крупные грузоперевозчики, экспедиторы, операторы портов и грузовых терминалов. В числе представленых компаний, имеющих собственный стенд, была и […]

read this article

13.05.2011

The first modules for the construction of Neurosurgery Centre in Novosibirsk

The first 71 modules for the construction of the Federal Centre for Neurosurgery in Novosibirsk have left the harbour Antwerp heading towards the harbour Perm. Up to now 185 modules have been dispatched from manufacturers works. At this date mobilization works for the construction site of the next centre have been put through and it […]

read this article

11.05.2011

First modules for construction of cardiology were sent from Germany to Kaliningrad

Delivery of all modules and complementary equipment is planned to be completed till the end of July 2011. First set of modules for construction of cardiovascular surgery was delivered on 10 of May 2011. Reportedly, vessel “Volgo-Balt-210” has left the German port Rostock and is going to Kaliningrad area. As it is known by “Klops.ru”, […]

read this article

06.05.2011

Delivery of modules and supplementary equipment for construction of Smolensk Health Center

165 truckloads of modules and 49 truckloads of supplementary equipment were delivered to the construction site of Smolensk inter-regional traumatology, orthopedics and endoprosthesis replacement center. Delivery of medical equipment was fulfilled by using two routes: 1. Cadolto plant in Krolpa – port of Rostock – port of St.Petersburg – Smolensk 2. Cadolto plant in Kadoltzburg […]

read this article

26.04.2011

Transportation of Viesmann equipment.

Project on delivery and customs clearing of Viesmann boiler installation took a start on April 2011. Boiler installation consists of 4 steam boilers sized 11,20 x 6,60 x 5,30 m; each of it weights around 75 tons. Also boiler installation includes 4 vapor prime movers and 500 units of components. Parts of boiler installation are […]

read this article

17.04.2011

Breakbulk Europe 2011, 18-20 Mai

On May 18-20th 2011 in Antwerp (Belgium) the conference Breakbulk Europe will take place, which is the most important annual event for all forwarders of the project freights. The exhibition BreakBulk Europe is the meeting point of freight owners and transporters who are ready to implement the most difficult transportations. The stands of the world […]

read this article

16.03.2011

Constructor

(Русский) В 2006 году вышло Постановление Правительства РФ о строительстве федеральных центров высоких медицинских технологий в восьми городах России – среди них 4 сердечно–сосудистой хирургии, два травматологии, ортопедии и эндопротезирования, один нейрохирургии и один научно–клинический центр детской гематологии, онкологии и иммунологии.

read this article

15.02.2011

Произведена выгрузка с теплохода “Flinterland” сорока медицинских модулей

12 февраля на терминале «МОБИ ДИК» в Кронштадте была произведена выгрузка с теплохода “Flinterland” сорока медицинских модулей для строительства медицинского федерального центра травматалогии, ортопедии и эндопротезирования в Смоленске, которое проводится в рамках национальной Программы «Здоровье». Непростая ледовая обстановка, мороз и ветер не стали препятствием для проведения этих работ. Автопоезда с дорогим грузом регулярно уходят из […]

read this article

08.02.2011

Discharging of the barge “Johanna” was finished

(Русский) Баржа Johanna с грузом проекта «Здоровье» по доставке модулей в Новосибирск успешно доставила 1-й лот модулей из Манхайма, Германия в Антверпен, Бельгия.

read this article

. . . Connecting continents